1、项目经理正在管理一个先进的计费系统项目。项目经理已经检查了现在的计费系统以及公司项目管理信息系统(PMIS)中的经验教训知识库。项目经理将可能收集更多的系统需求。项目经理下一步应该怎么做?
A project manager is leading in a state-of-the art billing system project.The project manager has checked the existing billing system,as well as the lessons learned repository in the company’s project management information system(PMIS).The project manager would like to gather more system requirements.What should the project manager do next?
A:参考所有的行业最佳实践
Refer to existing industry best practices.
B:咨询任何有经验的内部或外部团队
Consult any experienced internal or external group.
C:与外部主题专家(SME)一起工作
Work with external subject matter experts(SMEs).
D:与内部业务和技术支持资源一起工作
Work with internal business and technical support resources
正确答案:B。A选项不切实际,B选项包含C、D。
7、一家公司正在冒险进入一项新业务,但之前在该市场中没有经验,项目经理应使用什么工具或技术来收集需求?
A company is venturing into a new business but has no previous experience in that market. What tool or technique should the project manager use to collect requirements?
A:原型法
Prototypes
B:专家判断
Expert judgement
C:产品分析
Production analysis
D:制定决策
Decision making
正确答案:A。没经验,没有可用的组织过程资产,使用原型法征求用户意见,收集需求
10、完成一个项目的第一个可交付成果后,一位相关方告知该可交付成果不满足业务需求。 项目经理下一步应该怎么做?
After completion of a project’s first deliverable,a stakeholder advises that it does not fulfill the business requirements.What shoul