2024年4月12日发(作者:隐藏文件夹怎么显示)
1 Purpose
Definition of Safe Launch Procedure
2 Definitions
Launch Management
Launch Management of a serial product comprises all activities for planning, executing and
controlling of a product launch with the defined production systems. Launch management starts
with the pre production release and ends with the full ramp up and the process readiness of all
products, processes and production devices.
Safe Launch
Launch Management with risk oriented enhanced control activities.
Safe Launch Coordinator: Responsible for the implementation of the defined Safe Launch Plan.
He is in charge of rating the different Safe Launch Phases and defining the necessary corrective
actions. Based on the results he decides about end or continuation of Safe Launch according to
defined exit criteria. The development team in cooperation with the production site nominates the
Safe Launch coordinator; it can be a member of the project team or a production site employee.
3 Responsibilities
Project Team: risk assessment, definition of safe launch
Production location; supplier: execution of safe launch
4 Procedure
4.1 Definition of Safe Launch
Step 1: Risk assessment in kick off resp. design/Process Review (Definition of high impact
parts or process steps), see checklists CF-037 part 1
Decision for safe launch in review 3
Step 2: Documentation/preliminary performance assessment at initial sample or production
review
Review initial sampling data in respect to process and gage capability
see checklists CF-037 part 2
Decision for safe launch in review 4
4.2 Creation of Safe Launch Plan
see CF – 036
4.2.1 structure
CD-00053-EN, Version: 3 3 / 6
Product1
assembly
•A
•B
•C
•characteristic
•frequency
•gage
component•A
•B
•characteristic
Product2
•C
•frequency
•gage
............
4.2.2 Test Intervals
- tool dependant characteristics 3 parts first/last piece at set-up, shift change and tooling
replacement/adjustment
- controllable characteristics 100% if process capability not ok; otherwise according to SPC
sampling plan
- Attributive characteristics 100%
- all customer interface characteristics 100%
- Labels and part identification as well as packaging: 100% visual check as well as check
of the material index (MR) – see dock audit form
- Tracking of process capabilities of important characteristics (except go/no go)
Note: tests have to be carried out additional to production control plan
CD-00053-EN, Version: 3 4 / 6
4.3 Execution of Safe Launch
Theme responsible
Process readiness audit (see CD 008) internal
Process readiness audit (see CD 008) supplier
Performance of additional controls as defined per Safe Launch Plan
(first 5000 parts)
Quality location
STA
Supplier, location
Analysis of failures and definition of corrective actions Safe Launch
Coordinator
Repetition of Safe Launch Supplier, location
Remark: Safe Launch has to be repeated until 5000 parts with 0 defects
at safe launch checks are obtained
CD-00053-EN, Version: 3 5 / 6
- Production process
- Components
- Function in car
Training/discussion of drawings ZG/ZF
Discussion of important characteristics
Process elements
Control plan, gages
Participants: Coach (Line foreman)
Production workers (if possible all shifts)
MA
Quality responsible production
Process optimization team
Attention: product training has to be done additional to normal employee qualification
7.2 Recommended Forms for Tracking of Safe Launch (see Querverweise)
1. Safe Launch tracking sheet for all concerned parts
Recommended: FOR-Q-503 Safe launch Off Line Summary Template
2. Dock Audit Form
3. Supplier Safe Launch Tracking Sheet
4. Letter to Supplier
8 Revision history
1.0 first edition of document
2.0 more detailed definition of Safe Launch exit criteria
3.0 Definition of Safe launch coordinator
Addition of test volume
addition of recommended sheets
addition of product training
CD-00053-EN, Version: 3 6 / 6